Crane Control

De Knoop BV

Nieuws

01 2012
Dynamisch camera systeem
voor Hupac Antwerpen
12 2011
Commissioning container
tilting frame
08 2011
Commissioning ship-unloader
Belgium - River Schelde
04 2011
Verbetering dynamiek
lastbegrenzing STS
03 2011
Botsbeveiliging Liebherr
Ship To Shore karanen
07 2010
Service op afstand voor drie
STS containerkranen
Rotterdam - Waalhaven
05 2010
Service en onderhoud drie
Künz containerkranen
Antwerpen - Scheldelaan 800

nieuws

Project: commissioning tilting frame
Plaats: Rotterdam - Botlek
Eindklant: Bertschi BV
Levering: eind 2011

 

 

 




Crane Control BV provided assistance for the commissioning of a new container tilting frame. This frame can be used to tilt 20, 30 and 40 feet bulk containers and to transfer the exactly weighted load to another container.

The job was a multi disciplinary work with the following disciplines:
- Electric controls with a cat. 4 safety circuit & motor starter 37 kW
- Hydraulic system with hydro pack, control valves & tilting cylinder
- Compressed air system with 15 bar compressor for different functions
- Supervision and assembly works on site during a short time frame